MRP Run should not consider Sales Order which is more than 60 days

$
0
0

Hi All,

 

Thanks in advance.

 

Please help me and reply on this at earliest.

 

Requirement : During MRP run the Sales Order whose delivery date is more than 60 days from the sales order creation date should not considered during MRP Run.

 

Current System Scenario : MRP Type VB (Manual Reorder Point Planning) is being used. And no Strategy Group defined in MRP view.

 

Analysis already done : Set Planning Horizon to 60 Days and run MRP in sequence on NETCH 2311 but didn't work.

 

Kindly give your solutions.

 

Regards

Anish Verma