Greetings,
Can we able to set the lead time for Example : X supplier lead time is 1 month Firm next 3 months 50% fluctuations and beyond 100% fluctuations.
How can we set this details in SAP schedule agreement portion. so that if MRP run happen I don't want to check manually and change the details in SAP to transmit the schedules to suppliers.
by Senthilvelan,S